Pipeline trench spoil transformed into bedding sand onsite
Port Melbourne, VIC
While installing underground services in Port Melbourne, JHL Civil began screening trench spoil directly onsite using a FlipScreen bucket. Instead of hauling excavated soil away and importing bedding sand, operators screened the spoil to create reusable bedding material for pipe installation. This reduced truck movements, lowered project costs and kept the pipeline installation moving efficiently.
JHL Civil
Installing underground pipelines through dense urban areas creates a constant stream of excavated trench spoil. On many projects this material is removed from site while clean bedding sand is delivered separately for pipe installation. JHL Civil encountered this situation while working on service infrastructure in Port Melbourne, where space was limited and truck movements needed to be carefully managed. Much of the excavated material already contained fine sand suitable for pipe bedding if it could be separated from rocks and debris. However, processing the material traditionally would require fixed screening equipment or offsite handling. The team needed a way to quickly produce consistent bedding material within the trenching workflow itself.
Challenge
JHL Civil introduced a FlipScreen WL130 screening bucket to operate alongside the excavator during trenching works. As spoil was removed from the trench, it was placed directly into the rotating screening bucket. The screening mesh allowed fine sand and soil to fall through while larger stones and debris were retained. This produced a consistent, fine bedding material suitable for laying and supporting pipe sections. Because the FlipScreen travels with the excavator, screening could occur directly beside the trench without interrupting the pipe installation process. Operators could also change mesh sizes quickly if the project required different grades of material.
Solution
The introduction of the FlipScreen allowed JHL Civil to convert excavated spoil into a valuable construction resource. Bedding sand produced from screened trench material was reused immediately during pipeline installation, eliminating the need for large volumes of imported material. Truck movements to remove spoil were also significantly reduced, improving site safety and lowering transport costs. The ability to process spoil beside the trench helped streamline the installation sequence, keeping crews and machinery working continuously. The result was faster project delivery, improved material efficiency and a simpler approach to managing trench spoil on pipeline projects.
Result

FlipScreen WL130 used by JHL Civil to recover reusable material onsite
Pipelines
WL130
Pipeline trench spoil
Industry:
FlipScreen Model:
Material:
Pipeline trench spoil transformed into bedding sand onsite
Port Melbourne, VIC
Installing underground pipelines through dense urban areas creates a constant stream of excavated trench spoil. On many projects this material is removed from site while clean bedding sand is delivered separately for pipe installation. JHL Civil encountered this situation while working on service infrastructure in Port Melbourne, where space was limited and truck movements needed to be carefully managed. Much of the excavated material already contained fine sand suitable for pipe bedding if it could be separated from rocks and debris. However, processing the material traditionally would require fixed screening equipment or offsite handling. The team needed a way to quickly produce consistent bedding material within the trenching workflow itself.
Challenge
JHL Civil introduced a FlipScreen WL130 screening bucket to operate alongside the excavator during trenching works. As spoil was removed from the trench, it was placed directly into the rotating screening bucket. The screening mesh allowed fine sand and soil to fall through while larger stones and debris were retained. This produced a consistent, fine bedding material suitable for laying and supporting pipe sections. Because the FlipScreen travels with the excavator, screening could occur directly beside the trench without interrupting the pipe installation process. Operators could also change mesh sizes quickly if the project required different grades of material.
Solution
The introduction of the FlipScreen allowed JHL Civil to convert excavated spoil into a valuable construction resource. Bedding sand produced from screened trench material was reused immediately during pipeline installation, eliminating the need for large volumes of imported material. Truck movements to remove spoil were also significantly reduced, improving site safety and lowering transport costs. The ability to process spoil beside the trench helped streamline the installation sequence, keeping crews and machinery working continuously. The result was faster project delivery, improved material efficiency and a simpler approach to managing trench spoil on pipeline projects.
Result
Pipelines
WL130
FlipScreen WL130 used by JHL Civil to recover reusable material onsite
Pipeline trench spoil
Industry:
FlipScreen Model:
Material:

While installing underground services in Port Melbourne, JHL Civil began screening trench spoil directly onsite using a FlipScreen bucket. Instead of hauling excavated soil away and importing bedding sand, operators screened the spoil to create reusable bedding material for pipe installation. This reduced truck movements, lowered project costs and kept the pipeline installation moving efficiently.
JHL Civil
Pipeline trench spoil transformed into bedding sand onsite
Port Melbourne, VIC
Installing underground pipelines through dense urban areas creates a constant stream of excavated trench spoil. On many projects this material is removed from site while clean bedding sand is delivered separately for pipe installation. JHL Civil encountered this situation while working on service infrastructure in Port Melbourne, where space was limited and truck movements needed to be carefully managed. Much of the excavated material already contained fine sand suitable for pipe bedding if it could be separated from rocks and debris. However, processing the material traditionally would require fixed screening equipment or offsite handling. The team needed a way to quickly produce consistent bedding material within the trenching workflow itself.
Challenge
JHL Civil introduced a FlipScreen WL130 screening bucket to operate alongside the excavator during trenching works. As spoil was removed from the trench, it was placed directly into the rotating screening bucket. The screening mesh allowed fine sand and soil to fall through while larger stones and debris were retained. This produced a consistent, fine bedding material suitable for laying and supporting pipe sections. Because the FlipScreen travels with the excavator, screening could occur directly beside the trench without interrupting the pipe installation process. Operators could also change mesh sizes quickly if the project required different grades of material.
Solution
The introduction of the FlipScreen allowed JHL Civil to convert excavated spoil into a valuable construction resource. Bedding sand produced from screened trench material was reused immediately during pipeline installation, eliminating the need for large volumes of imported material. Truck movements to remove spoil were also significantly reduced, improving site safety and lowering transport costs. The ability to process spoil beside the trench helped streamline the installation sequence, keeping crews and machinery working continuously. The result was faster project delivery, improved material efficiency and a simpler approach to managing trench spoil on pipeline projects.
Result
Pipelines
WL130
FlipScreen WL130 used by JHL Civil to recover reusable material onsite
Pipeline trench spoil
Industry:
FlipScreen Model:
Material:

While installing underground services in Port Melbourne, JHL Civil began screening trench spoil directly onsite using a FlipScreen bucket. Instead of hauling excavated soil away and importing bedding sand, operators screened the spoil to create reusable bedding material for pipe installation. This reduced truck movements, lowered project costs and kept the pipeline installation moving efficiently.
JHL Civil
6 a.m - 9 p.m (Mon - Sun)
contact@strongx.com
+259 (0) 256 215
